Background
Due to permitting delays, this project has been moved to an estimated early 2025 start. The District of Oak Bay intends to select a contractor in early 2025.
The District will be undertaking infrastructure upgrades along Estevan Ave from the Willows Beach Esplanade to Heron St, including work on a stretch of Lincoln Rd. This work includes:
- Pavement removal
- Subsurface trenching for utility replacement
- Road and sidewalk improvements, dependent on trenching
Location
This is phase one of the project, and the work will take place on:
- Estevan Ave. from Willows Beach to Heron St.
- Lincoln Road, from Estevan to Burdick Ave.