Uplands Sewer Separation Project - Humber Catchment

Share Uplands Sewer Separation Project - Humber Catchment on Facebook Share Uplands Sewer Separation Project - Humber Catchment on Twitter Share Uplands Sewer Separation Project - Humber Catchment on Linkedin Email Uplands Sewer Separation Project - Humber Catchment link

Welcome to the project page for the Uplands Sewer Separation project in the Humber Catchment. This page provide project information and updates on the progress of the project.

Where we are today

Early April 2024

Windley Contractling Ltd. will mobilize on site to setup equipment, install construction signage, perform utility locates and start delivering of materials.

Late April to June 2024

  • Installation of the storm main on Beach Dr. between Ripon and Midland Road, and then on Ripon Road from the storm outfall to Beach Drive.
  • Rock Removal on Exeter Road between Lansdowne and Beach Drive.

Location of new storm main and rock removal – April to June 2024


Location of Site Office & Laydown Area – Cattle Point (long term)


Background

This project is the first phase of a sewer separation project in the Uplands neighbourhood, the Humber Catchment. The existing, combined collection system is comprised of two main catchment areas – Humber and Rutland.

The system was constructed in the 1930’s using a single pipe to collect both sanitary sewage (toilets, showers, and sinks) and storm water (rainwater leaders, foundation drains and catch basins in the roads), discharging into the ocean at the ends of Humber Road and Rutland Road. In the early 1990’s, these combined systems were redirected into the newly constructed Capital Regional District pump stations at Humber and Rutland and pumped into a trunk sewer main on Beach Drive. However, during large storm events, which are becoming more frequent, the flow into the pump stations can at times exceed the capacity of the pumps and the excess effluent discharges through the old outfalls into the ocean. In 2016, six options were developed for separating the combined sewer system into separate sanitary sewer and storm sewer systems. The option selected by Council, after a public consultation process, was a new gravity storm sewer system. The existing combined sewer system will become the new separate sanitary sewer system.

The Uplands Sewer Separation project is one of Oak Bay’s major infrastructure commitments under the regional Core Area Liquid Waste Management Plan (CALWMP). Once both phases are complete, the project will eliminate sanitary sewer overflows to the nearshore marine environment, thereby significantly improving health and environmental protection. It will also bring the municipality in compliance with provincial and federal wastewater and environmental protection legislation. Notably, the Province of BC has directed that construction of the Humber catchment area must be complete by 2025.

Physical works that will be undertaken as part of the first phase (Humber catchment construction) include:

  • construction of a new gravity stormwater system (approximately 3.5 km), including mains, manholes, catch basins and leads;
  • installation of new service connections to each house (approximately 120);
  • installation of new streetlights, and
  • construction of two new ocean outfalls.


Welcome to the project page for the Uplands Sewer Separation project in the Humber Catchment. This page provide project information and updates on the progress of the project.

Where we are today

Early April 2024

Windley Contractling Ltd. will mobilize on site to setup equipment, install construction signage, perform utility locates and start delivering of materials.

Late April to June 2024

  • Installation of the storm main on Beach Dr. between Ripon and Midland Road, and then on Ripon Road from the storm outfall to Beach Drive.
  • Rock Removal on Exeter Road between Lansdowne and Beach Drive.

Location of new storm main and rock removal – April to June 2024


Location of Site Office & Laydown Area – Cattle Point (long term)


Background

This project is the first phase of a sewer separation project in the Uplands neighbourhood, the Humber Catchment. The existing, combined collection system is comprised of two main catchment areas – Humber and Rutland.

The system was constructed in the 1930’s using a single pipe to collect both sanitary sewage (toilets, showers, and sinks) and storm water (rainwater leaders, foundation drains and catch basins in the roads), discharging into the ocean at the ends of Humber Road and Rutland Road. In the early 1990’s, these combined systems were redirected into the newly constructed Capital Regional District pump stations at Humber and Rutland and pumped into a trunk sewer main on Beach Drive. However, during large storm events, which are becoming more frequent, the flow into the pump stations can at times exceed the capacity of the pumps and the excess effluent discharges through the old outfalls into the ocean. In 2016, six options were developed for separating the combined sewer system into separate sanitary sewer and storm sewer systems. The option selected by Council, after a public consultation process, was a new gravity storm sewer system. The existing combined sewer system will become the new separate sanitary sewer system.

The Uplands Sewer Separation project is one of Oak Bay’s major infrastructure commitments under the regional Core Area Liquid Waste Management Plan (CALWMP). Once both phases are complete, the project will eliminate sanitary sewer overflows to the nearshore marine environment, thereby significantly improving health and environmental protection. It will also bring the municipality in compliance with provincial and federal wastewater and environmental protection legislation. Notably, the Province of BC has directed that construction of the Humber catchment area must be complete by 2025.

Physical works that will be undertaken as part of the first phase (Humber catchment construction) include:

  • construction of a new gravity stormwater system (approximately 3.5 km), including mains, manholes, catch basins and leads;
  • installation of new service connections to each house (approximately 120);
  • installation of new streetlights, and
  • construction of two new ocean outfalls.


Page last updated: 05 Apr 2024, 10:53 AM