Welcome to the project page for the Uplands Sewer Separation project in the Humber Catchment. This page provide project information and updates on the progress of the project.

Where we are today

Midland Road: Concrete curb restoration complete.

Ripon & Norfolk Road: Concrete curb and sidewalk restoration underway. Installation of streetlight poles underway.

Exeter Road: Concrete curb & sidewalk restoration underway. Installation of streetlight poles underway.

Beach Drive: Concrete curb & sidewalk restoration underway.

Lansdowne Road: Concrete curb & sidewalk restoration underway. Installation of streetlight poles underway.

Upcoming Work - December 2025

All Roads
  • Continuing with concrete curb & sidewalk restoration and topsoil reinstatement. Work will be done as the weather permits.
  • Continuing with installation of the streetlight poles and fixtures. Commissioning of lights anticipated mid-December 2025.
  • Site cleanup.
  • Paving is planned to start early 2026.

*The anticipated completion dates above are based on the Contractor’s current schedule, and are subject to change due to weather, delays, or changes within other areas of the project.

Midland Road
  • Grading and asphalt paving. Work will be done as the weather permits.

Uplands Streetlights

The District acknowledges that recent construction has impacted the streetlight system, resulting in damage to existing wiring and causing outages on Beach Drive and Exeter Road. Locating the source of the damage has been challenging; however, we have expedited the commissioning of the new lighting system. The new lights on Beach Drive and Exeter Road are scheduled to be operational by December 4, 2025. We appreciate your patience as we work to restore safe and reliable lighting in the area.

Ripon Road Temporary Stockpile

April 30, 2025 -- A new temporary soil stockpile location is needed to accommodate archaeological screening of soils identified along Beach Drive. The Ripon Road cul-de-sac has been identified as a preferred location, approved by the province.

This stockpile is expected to be in place, starting May 1, for six to eight weeks (dependent on finds). Measures will be taken by the contractor to limit environmental impacts including dust and runoff.

  • Access will be maintained for local resident traffic, driveway access only.
  • Access to the Yacht Club will not be impacted.

We thank you for your understanding with this needed location during the project.

Construction Impacts

As part of the Uplands Sewer Separation & Watermain Replacement project, we will be performing storm drain work within both lanes on Beach Drive between Lansdowne Road and Ripon Road.

During this work Beach Drive between Lansdowne Road and Ripon Road will be closed to non-local traffic between the hours of 7:00 a.m. and 5:00 p.m.

Location:

  • Beach Drive between Lansdowne Road and Ripon Road.

Closure Dates and Times

  • Starting September 2, 2025, to September 16, 2025.
  • Hour of work – Monday to Friday, 7:00 AM to 5:00 PM.
  • Beach Drive will be open to traffic during non-working hours.

Traffic Impacts

  • Beach Drive will be open to local traffic only.
  • Access to private driveways will be maintained. There may be short durations of time where driveways will be inaccessible.
  • Waste collection services, recycling, Canada Post and other delivery/pickup services will not be disrupted.
  • Pedestrian and Cyclist will have access though the site using the sidewalk.
  • Non-local traffic will be detoured using Lansdowne Road.
  • BC Transit stops may be relocated or closed, please refer to the BC Transit website for updates: www.bctransit.com

Disturbance to water or sewer services is not expected. Residents will be notified a minimum 24 hours of any planned disruption.

News Feed

Survey